Case Study
Pinnacle Develop — Multifamily Developer, Austin TX
The Challenge
The supply problems slowing production.
The Solution
What Modular Openings deployed.
Implementation Timeline
From assessment to live supply.
1
Factory Assessment & BOM Review
Audited vendor relationships, SKU fragmentation, and unit-type specs. Established program baseline. Weeks 1–2.
2
Program Design & Vendor Alignment
Standardized SKU families mapped to each unit type. Vendors selected and aligned to volume commitments. Weeks 3–5.
3
Pilot Delivery & Validation
Pilot across 2 unit types. Factory ops validated pack formats, labeling, and hardware kit completeness. Weeks 6–9.
4
Full Program Launch
All unit types brought online. Delivery cadence established matching factory production rate. Week 10+.
Next Case Study
See how More Case Studies did it.
Every supply program starts with the same question: what's slowing your factory down?